UIUC Ceramics Building Restroom Renovation

Renovation of existing toilet rooms to provide accessibility and updates; addition of new toilet rooms as shown, replacement of electrical switchgear, and the associated building work. Environmental abatement will be required per the drawings and specifications and will include the removal and disposal of: asbestos containing floor tile, asbestos containing pipe insulation, and lead-based paint.
  Addendum 1 (click to expand/collapse)
There were 2 specification sections that are included in the project manual, but were not listed in the Table of Contents. They are:
26 13 00 Medium Voltage Switchgear
26 13 16 Medium Voltage Fused Switch Interrupter
We have issued Addendum No. 01 which updated the Table of Contents to list these 2 sections.
This is available for download to registered users. Log in now
Name Size
U18027 Addendum No. 1 118.2 KB
_00_Project Manual TOC 96.3 KB
  Addendum #2 (click to expand/collapse)
  Addendum 3 (click to expand/collapse)
  Addendum 4 (click to expand/collapse)
The UIUC Ceramics Building project Addendum No. 4: Answers to Bid Questions. Please note that there are no drawings associated with this addendum. Posted 9-6-19
This is available for download to registered users. Log in now
Name Size
11_U18027 Addendum No. 4 & Bid Questions 127.1 KB
  Bid Tab Division 1 (click to expand/collapse)
This is available for download to registered users. Log in now
Name Size
U18027 Div 1 Bid Tab 49.9 KB
  Bid Tabs for Divisions 2,4,5 (click to expand/collapse)
This is available for download to registered users. Log in now
Name Size
U18027 Bid Tab 09 10 19 155.9 KB